機材が実際に現場へ到着し稼働するまでの流れ

顧客名は秘密保持のため非公開とし、現場条件、構成ロジック、検証可能な範囲は記載しています。数値はプロジェクト期間中の実測値またはレンジ値です。

プロジェクトニーズを投稿する

Filter by industry and country

6 / 6

業界
国
Roads & municipalナイジェリア・ラゴス2024年 · 約7ヶ月

Equipment package for Lagos urban road rehabilitation

A contractor needed 32 km of road rehabilitation within one rainy-season window; the platform built a schedule-driven equipment list with local operators and parts.

サイト認証

A one-week delay would compress compaction and paving windows, and local parts lead times made downtime a major risk.

  • Equipment split across compaction, paving and haulage to avoid single-brand downtime.
  • Wear-part kits shipped with the fleet plus two standby rollers to cut recovery time.
  • Twelve operators matched from the local pool with model handover and safety induction.

32 km

Road rehabilitated

> 92%

車両稼働状況

45日

Mobilisation

詳細事例を読む
共有FacebookXWhatsAppLinkedIn
Equipment package for Lagos urban road rehabilitation
Mining & processingザンビア・銅鉱山地帯2023–2025 · 段階的納品

Load-and-haul combination for an open-pit copper mine

Plant expansion raised stripping volumes; the platform reconfigured the fleet with 90 t excavators and 60 t wide-body tippers, adding a parts warehouse.

サイト認証

Truck tonnage did not match loading capacity, increasing queue time, fuel and tyre costs.

  • Truck-to-loader ratio recalculated from cycle times to cut mutual waiting.
  • Fast-moving parts pre-positioned locally with 48-hour coverage.
  • Driver fatigue management and inspection routines reduced unplanned downtime.

5 : 1

Truck-loader ratio

48 h

Parts lead time

+ 30%

剥離能力

詳細事例を読む
共有FacebookXWhatsAppLinkedIn
Load-and-haul combination for an open-pit copper mine
Lifting & erectionケニア・ナイロビ2025年 · 約2ヶ月

Steel structure erection for a logistics warehouse

A large-span warehouse with restricted internal roads: an 80 t mobile crane and lift plan supported night-time road closures.

サイト認証

The site sits in a live logistics park; no daytime road occupation, leaving a four-hour night window.

  • Pre-assembly plus panelised lifts shortened each lift cycle.
  • Load charts verified per radius, with superlift and counterweight plan.
  • Local signallers and safety officers coordinated with night lighting and exclusion zones.

1,850 t

Steel erected

4 h / day

Night window

68日

期間

詳細事例を読む
共有FacebookXWhatsAppLinkedIn
Steel structure erection for a logistics warehouse
Ports & logisticsアンゴラ・ルアンダ2024–2025 · 段階的到着

Terminal tractors and handling equipment for a port yard

With rising yard throughput, the platform supplied terminal tractors, reach stackers and forklifts, coordinating port access and on-site service.

サイト認証

The port applies its own emission, noise and access rules, and parts must be replenished by sea.

  • Models selected against the port access checklist with early technical submissions.
  • Six-month parts forecast consolidated into vessel shipments.
  • On-site technicians covered first-year warranty and operator training.

18台

Handling units

By vessel

Parts supply

12か月

現地サービス

詳細事例を読む
共有FacebookXWhatsAppLinkedIn
Terminal tractors and handling equipment for a port yard
Agriculture & processingエチオピア・アディスアベバ2025年 · 約5ヶ月

Turnkey processing line for an agro-processing plant

Cleaning, drying and packaging delivered as one line, with OEM engineers, customs clearance and commissioning coordinated.

サイト認証

Volatile grid power at the site required voltage stabilisation and backup planning at selection stage.

  • Motors and stabilisers configured to local voltage and frequency.
  • Segmented shipping and on-site assembly reduced handling difficulty.
  • Local crew trained for daily cleaning and wear-part replacement.

26セット

Line equipment

38日

Commissioning

22 people

現地研修

詳細事例を読む
共有FacebookXWhatsAppLinkedIn
Turnkey processing line for an agro-processing plant
中古設備コンゴ民主共和国 · ルブンバシ2025年 · 約3ヶ月

中古車両群の一括点検と納品

A budget-constrained buyer sourced nine used excavators backed by 128-point reports, hour verification and arrival re-inspection.

サイト認証

Used equipment information is opaque, making hours and structural condition hard to verify before shipping.

  • A unified checklist covering hydraulics, structure, electrics and undercarriage.
  • Hours and service records cross-checked with risk grading for anomalies.
  • Local service points re-inspect on arrival, with discrepancies handled per contract.

9台

納品台数

128 points

検査ポイント

9 / 9

Arrival re-check

詳細事例を読む
共有FacebookXWhatsAppLinkedIn
Batch inspection and delivery of a used fleet

Describe the site, get an executable configuration

場所、スケジュール、作業範囲、予算帯を共有してください。プラットフォームは国別エージェントとOEMをマッチングし、機器リスト、書類要件、人員配置アドバイスを提供します。

サービスパートナーになる

RELATED

配送能力の確認