A large-span warehouse with restricted internal roads: an 80 t mobile crane and lift plan supported night-time road closures.

Steel structure erection for a logistics warehouse
Client name withheld for confidentiality; figures are measured or ranged over the project period.

1,850 t

Steel erected

4 h / day

Night window

68 days

Duration

CHALLENGE

Site challenge

The site sits in a live logistics park; no daytime road occupation, leaving a four-hour night window.

APPROACH

What we did

  1. 01Pre-assembly plus panelised lifts shortened each lift cycle.
  2. 02Load charts verified per radius, with superlift and counterweight plan.
  3. 03Local signallers and safety officers coordinated with night lighting and exclusion zones.