Roads & municipalNigeria · Lagos2024 · about 7 months
Equipment package for Lagos urban road rehabilitation
A contractor needed 32 km of road rehabilitation within one rainy-season window; the platform built a schedule-driven equipment list with local operators and parts.

32 km
Road rehabilitated
> 92%
Fleet availability
45 days
Mobilisation
CHALLENGE
Site challenge
A one-week delay would compress compaction and paving windows, and local parts lead times made downtime a major risk.
APPROACH
What we did
- 01Equipment split across compaction, paving and haulage to avoid single-brand downtime.
- 02Wear-part kits shipped with the fleet plus two standby rollers to cut recovery time.
- 03Twelve operators matched from the local pool with model handover and safety induction.