Agriculture & processingEthiopia · Addis Ababa2025 · about 5 months
Turnkey processing line for an agro-processing plant
Cleaning, drying and packaging delivered as one line, with OEM engineers, customs clearance and commissioning coordinated.

26 sets
Line equipment
38 days
Commissioning
22 people
Local training
CHALLENGE
Site challenge
Volatile grid power at the site required voltage stabilisation and backup planning at selection stage.
APPROACH
What we did
- 01Motors and stabilisers configured to local voltage and frequency.
- 02Segmented shipping and on-site assembly reduced handling difficulty.
- 03Local crew trained for daily cleaning and wear-part replacement.