Steel structure erection for a logistics warehouse

A large-span warehouse with restricted internal roads: an 80 t mobile crane and lift plan supported night-time road closures.

Steel structure erection for a logistics warehouse
Имя клиента скрыто в целях конфиденциальности; показатели измерены или указаны диапазоном за период проекта.

1,850 t

Steel erected

4 ч / день

Night window

68 дней

Длительность

CHALLENGE

Проверка сайта

The site sits in a live logistics park; no daytime road occupation, leaving a four-hour night window.

APPROACH

Выполненные работы

  1. 01Pre-assembly plus panelised lifts shortened each lift cycle.
  2. 02Load charts verified per radius, with superlift and counterweight plan.
  3. 03Local signallers and safety officers coordinated with night lighting and exclusion zones.