BeastDanceBEASTDANCE.COM
Lifting & erectionケニア・ナイロビ2025年 · 約2ヶ月

Steel structure erection for a logistics warehouse

A large-span warehouse with restricted internal roads: an 80 t mobile crane and lift plan supported night-time road closures.

Steel structure erection for a logistics warehouse
機密保持のため顧客名は非公開。数値はプロジェクト期間中に測定または範囲指定されたもの。

1,850 t

Steel erected

4 h / day

Night window

68日

期間

CHALLENGE

サイト認証

The site sits in a live logistics park; no daytime road occupation, leaving a four-hour night window.

APPROACH

実績

  1. 01Pre-assembly plus panelised lifts shortened each lift cycle.
  2. 02Load charts verified per radius, with superlift and counterweight plan.
  3. 03Local signallers and safety officers coordinated with night lighting and exclusion zones.
共有FacebookXWhatsAppLinkedIn