Lifting & erectionKenia · Nairobi2025 · aproximadamente 2 meses

Steel structure erection for a logistics warehouse

A large-span warehouse with restricted internal roads: an 80 t mobile crane and lift plan supported night-time road closures.

Steel structure erection for a logistics warehouse
Nombre del cliente omitido por confidencialidad; las cifras son medidas o estimadas durante el período del proyecto.

1,850 t

Steel erected

4 h / día

Night window

68 días

Duración

CHALLENGE

Desafío del sitio

The site sits in a live logistics park; no daytime road occupation, leaving a four-hour night window.

APPROACH

Qué hicimos

  1. 01Pre-assembly plus panelised lifts shortened each lift cycle.
  2. 02Load charts verified per radius, with superlift and counterweight plan.
  3. 03Local signallers and safety officers coordinated with night lighting and exclusion zones.