Lifting & erectionKenia · Nairobi2025 · ca. 2 Monate

Steel structure erection for a logistics warehouse

A large-span warehouse with restricted internal roads: an 80 t mobile crane and lift plan supported night-time road closures.

Steel structure erection for a logistics warehouse
Kundenname aus Vertraulichkeitsgründen anonymisiert; Werte sind gemessen oder als Spanne über den Projektzeitraum angegeben.

1,850 t

Steel erected

4 h / Tag

Night window

68 Tage

Dauer

CHALLENGE

Website-Herausforderung

The site sits in a live logistics park; no daytime road occupation, leaving a four-hour night window.

APPROACH

Was wir getan haben

  1. 01Pre-assembly plus panelised lifts shortened each lift cycle.
  2. 02Load charts verified per radius, with superlift and counterweight plan.
  3. 03Local signallers and safety officers coordinated with night lighting and exclusion zones.