Lifting & erectionKenia · Nairobi2025 · ca. 2 Monate
Steel structure erection for a logistics warehouse
A large-span warehouse with restricted internal roads: an 80 t mobile crane and lift plan supported night-time road closures.

1,850 t
Steel erected
4 h / Tag
Night window
68 Tage
Dauer
CHALLENGE
Website-Herausforderung
The site sits in a live logistics park; no daytime road occupation, leaving a four-hour night window.
APPROACH
Was wir getan haben
- 01Pre-assembly plus panelised lifts shortened each lift cycle.
- 02Load charts verified per radius, with superlift and counterweight plan.
- 03Local signallers and safety officers coordinated with night lighting and exclusion zones.