Steel structure erection for a logistics warehouse

A large-span warehouse with restricted internal roads: an 80 t mobile crane and lift plan supported night-time road closures.

Steel structure erection for a logistics warehouse
اسم العميل محجوب للسرية؛ الأرقام مقاسة أو ضمن نطاق خلال فترة المشروع.

1,850 t

Steel erected

4 ساعات / يوم

Night window

68 يوم

المدة

CHALLENGE

تحدي الموقع

The site sits in a live logistics park; no daytime road occupation, leaving a four-hour night window.

APPROACH

ما قمنا به

  1. 01Pre-assembly plus panelised lifts shortened each lift cycle.
  2. 02Load charts verified per radius, with superlift and counterweight plan.
  3. 03Local signallers and safety officers coordinated with night lighting and exclusion zones.