Roads & municipalナイジェリア・ラゴス2024年 · 約7ヶ月

Equipment package for Lagos urban road rehabilitation

A contractor needed 32 km of road rehabilitation within one rainy-season window; the platform built a schedule-driven equipment list with local operators and parts.

Equipment package for Lagos urban road rehabilitation
機密保持のため顧客名は非公開。数値はプロジェクト期間中に測定または範囲指定されたもの。

32 km

Road rehabilitated

> 92%

車両稼働状況

45日

Mobilisation

CHALLENGE

サイト認証

A one-week delay would compress compaction and paving windows, and local parts lead times made downtime a major risk.

APPROACH

実績

  1. 01Equipment split across compaction, paving and haulage to avoid single-brand downtime.
  2. 02Wear-part kits shipped with the fleet plus two standby rollers to cut recovery time.
  3. 03Twelve operators matched from the local pool with model handover and safety induction.