Roads & municipalNigeria · Lagos2024 · aproximadamente 7 meses

Equipment package for Lagos urban road rehabilitation

A contractor needed 32 km of road rehabilitation within one rainy-season window; the platform built a schedule-driven equipment list with local operators and parts.

Equipment package for Lagos urban road rehabilitation
Nombre del cliente omitido por confidencialidad; las cifras son medidas o estimadas durante el período del proyecto.

32 km

Road rehabilitated

> 92%

Disponibilidad de flota

45 días

Mobilisation

CHALLENGE

Desafío del sitio

A one-week delay would compress compaction and paving windows, and local parts lead times made downtime a major risk.

APPROACH

Qué hicimos

  1. 01Equipment split across compaction, paving and haulage to avoid single-brand downtime.
  2. 02Wear-part kits shipped with the fleet plus two standby rollers to cut recovery time.
  3. 03Twelve operators matched from the local pool with model handover and safety induction.