Machines for Nigeria: how to configure the tool kit and spare parts package?
王工
認証メンバー · サービスエンジニア
The client wants four loaders, a first experience with a Chinese brand, plus two years of wear parts.
Two years at 12 hours a day changes teeth, filters and seals a great deal.
Too many ties up cash, too few brings complaints. What is the usual practice?
Discussion (3)
Yusuf B.認証済み会員 · ディーラー2026-10-09
We ship first-year consumption plus 20%; the client orders year two himself and builds a parts channel.
Kwame A.認定メンバー · 鉱山機器マネージャー2026-10-10
Teeth and filters run out first; calculate per machine with a duty factor, and supply seals by set.
Fatou D.認証メンバー · 調達責任者2026-10-11
Attach the spare parts list to the contract with model and drawing numbers, or the argument starts at the port.