Client wants delivery in 45 days, the factory slots 70: how to negotiate?

李

李工

عضو موثوق · فحص التصدير

Six 20 t excavators, and the client wants shipment in 45 days; standard scheduling is 70.

That is 25 days short. The factory wants 4% for a priority slot and must check hydraulic parts stock.

Passing the premium to the client risks the order; absorbing it kills margin. Any other way?

Discussion (3)

  • Ade O.عضو موثّق · مسؤول المشتريات2026-10-20

    Split the delivery: two units now to start work, four at 65 days. Clients usually accept staged arrival.

  • 王工عضو موثّق · مهندس خدمات2026-10-21

    Find the real bottleneck. Painting and commissioning can often be compressed; with hydraulic parts in stock, 55 days is possible.

  • Grace W.عضو موثق · كبير مهندسي المشاريع2026-10-21

    Put staged shipment and penalties in the contract; a verbal promise of 45 days turns into daily risk.