Chinese loaders in Cameroon: paint blistered in two months, process or shipping?

S

Samuel O.

Miembro verificado · Ingeniero de servicio

Five 5 t loaders reached Douala two months ago; three have blisters on the counterweight and lower frame.

Blisters sit where dunnage and straps touched the machines during shipping.

The factory blames sea humidity; we suspect surface preparation. How do we tell?

Discussion (3)

  • ChenMiembro verificado · Inspección de exportación2026-09-27

    Cut one blister open: rust starting at bare metal means preparation; dry paint with no rust points to condensation.

  • Rui C.Miembro verificado · Inspección de exportación2026-09-28

    Condensation at dunnage is common. Anti-rust oil and desiccant cost little and are worth making standard.

  • Fatou D.Miembro verificado · Responsable de compras2026-09-28

    Photograph before touching up; claims need the factory inspection record, which many orders skip.