FijadoCírculo de Ingeniería MineraZambia2026-10-28

Zambia copper pit: is a 1.9 m³ bucket too small for a 21 t excavator?

M

Mwila K.

Miembro verificado · Gerente de equipos mineros

Bench height is 10 m, the material is weathered copper ore, bulk density about 2.1 t per cubic metre.

Our 21 t machine runs a 1.9 m³ bucket; a 40 t truck takes nine passes and waits 40 seconds.

Should we move to 2.3 m³ or add a 30 t machine? Anyone on similar ground, please share numbers.

Discussion (3)

  • Grace W.Miembro verificado · Ingeniero jefe de proyecto2026-10-29

    At the same bench height we ran 2.3 m³: cycle time fell from 26 to 24 seconds, but teeth wore about 30% faster and the face had to stay level.

  • Chanda M.Miembro verificado · Ingeniero de servicio2026-10-30

    Check pump flow first. With a bigger bucket the relief valve stays open longer, and rising oil temperature is the first sign of a mismatch.

  • Ade O.Miembro verificado · Responsable de compras2026-10-31

    Do not look only at shift output: 40 seconds of waiting costs about 30 bucket loads a day. A second machine pays back in roughly 14 months, if the roads hold.

Respuestas recientes en este hilo, ordenadas por fecha de publicación

Unirse a la discusión

Inicia sesión para responder; el contenido aparece tras la revisión.

Iniciar sesión para responder