Safety & ComplianceSouth Africa2026-09-16

南非井控与消防配置核查,验收前要准备哪些资料?

J

João P.

认证用户 · 井控与 HSE 主管

The wellsite is set up for 5,000 m wells, with a 2FZ35-105 BOP stack and one kill and one choke manifold rated 105 MPa.

Looking at west coast oil, gas and refining assets, the supervisor asks for pressure-test records, NDT reports and operator qualifications, some of them only in English.

Looking at west coast oil, gas and refining assets, which document list and on-site check order avoids finding gaps the week of acceptance?

Discussion (3)

  • Fatou D.认证用户 · 钻井监督2026-09-17

    In Saldanha, match certificates to the equipment list, then check pressure-test dates; expired items fail on the spot.

  • Ifeanyi O.认证用户 · 培训负责人2026-09-18

    Qualifications must cover the actual crew; a new hand without a certificate blocks acceptance. Check the list of 9 names first.

  • Kwame A.认证用户 · 消防系统工程师2026-09-19

    What we see at Saldanha is that fire pumps need measured flow and head, not just nameplate data; the acceptance team usually starts them on site.

Recent replies in this thread, ordered by posting time