南非井控与消防配置核查,验收前要准备哪些资料?
João P.
认证用户 · 井控与 HSE 主管
The wellsite is set up for 5,000 m wells, with a 2FZ35-105 BOP stack and one kill and one choke manifold rated 105 MPa.
Looking at west coast oil, gas and refining assets, the supervisor asks for pressure-test records, NDT reports and operator qualifications, some of them only in English.
Looking at west coast oil, gas and refining assets, which document list and on-site check order avoids finding gaps the week of acceptance?
Discussion (3)
Fatou D.认证用户 · 钻井监督2026-09-17
In Saldanha, match certificates to the equipment list, then check pressure-test dates; expired items fail on the spot.
Ifeanyi O.认证用户 · 培训负责人2026-09-18
Qualifications must cover the actual crew; a new hand without a certificate blocks acceptance. Check the list of 9 names first.
Kwame A.认证用户 · 消防系统工程师2026-09-19
What we see at Saldanha is that fire pumps need measured flow and head, not just nameplate data; the acceptance team usually starts them on site.
Recent replies in this thread, ordered by posting time
Join the Discussion
Sign in to reply; content appears after review.
Log in to Reply