南非模块化炼厂,工厂预制验收该盯哪几项?

C

Chidi N.

认证用户 · 成套装置项目经理

The plant splits into 16 modules, the widest at 3.4 m, shipping to Saldanha.

What we see at Saldanha is that the contract sets factory prefabrication at no less than 80% but does not define pre-commissioning acceptance criteria.

In Saldanha, which records belong in the factory acceptance, and what must be retested on site?

Discussion (3)

  • Thabo M.认证用户 · 质量与检验2026-03-23

    In Saldanha, file pipe pressure tests, NDT and electrical loop tests by module; anything missing gets redone on site.

  • Yasmine K.认证用户 · 仪控调试2026-03-24

    On our side in Saldanha, pre-commissioning must prove interlock actions, not just screen states; simulated signals will not convince the acceptance team.

  • Chidi N.认证用户 · 现场安装经理2026-03-25

    Looking at west coast oil, gas and refining assets, check inter-module interfaces at the factory; mismatches found on site mean cutting and re-welding at the highest cost.