乌干达艾伯特湖油田伴生气发电,和柴油机组比该怎么算账?
Amina B.
认证用户 · 场站动力主管
The processing station runs three 500 kW diesel sets about 480 hours a month, with fuel trucked from Hoima.
Associated gas swings from about 7,200 m³ by day to 3,800 m³ at night, and a full sulphur analysis has not been done.
In Hoima, should we start with gas gensets or go straight to CCHP, given the present load profile?
Discussion (3)
Chidi N.认证用户 · 燃气机组服务工程师2026-10-24
In Hoima, do the full gas analysis first; high sulphur shortens the overhaul interval noticeably, and that cost cannot be skipped.
Fatou D.认证用户 · 能源项目经理2026-10-25
Looking at Lake Albert fields, with an electrical load only, gas gensets are the steadier first step; CCHP should wait for a firm heat demand, otherwise the waste heat is thrown away.
Ifeanyi O.认证用户 · 电气工程师2026-10-26
Size on the lowest stable flow, 3,800 m³, and cover peaks with diesel; do not let gas swings become shutdowns.
Recent replies in this thread, ordered by posting time