Tanzania section with a 4-month rainy season: how to schedule earthworks?

P

Paulo M.

Miembro verificado · Ingeniero jefe de proyecto

Twenty-month section, four months of rain, 380,000 m³ of earthworks.

Last rainy season we lost 40 days and paid standing-time claims.

We want to pull earthworks forward, but land handover is three months late.

Discussion (3)

  • Grace W.Miembro verificado · Ingeniero jefe de proyecto2026-10-03

    Do low areas and high fills in the dry season, switch to structures and stockpiling in the rains; sequence it early.

  • Bakary T.Miembro verificado · Gerente de equipos mineros2026-10-04

    Record the handover delay in writing and claim time; otherwise standing time in the rains is your risk.

  • Chanda M.Miembro verificado · Ingeniero de servicio2026-10-05

    Use the rains for maintenance; utilisation is low anyway, and it beats failures in the dry season.