Construction circleSaudi Arabia2026-10-31

Riyadh metro station night pour: how to schedule pumps and crews?

F

Faisal A.

Verified member · Project chief engineer

The Riyadh metro station is entering its main pour. Site temperature approaches 45°C by day, and the engineer only allows night pours.

One 56 m pump covers two work faces, but there are only two vibration crews, and night access is restricted by traffic rules.

How should pumps and crews be balanced, and how should curing and test cubes follow the night shift?

Discussion (3)

  • Marek P.Verified member · Construction manager2026-11-01

    Size the pump by hourly output, not by the number of faces; with a short night window, a spare pump beats an extra one.

  • Ahmed S.Verified member · Concrete supplier2026-11-02

    Tie the batching plant, transport and site permits into one night plan; material breaks are more common than equipment failure.

  • Lucas R.Verified member · Quality lead2026-11-03

    Take test cubes by pour batch, not by day or night shift; record placing temperature and covering time.

Recent replies in this thread, ordered by posting time

Join the Discussion

Sign in to reply; content appears after review.

Log in to Reply