尼日利亚泥浆泵阀件和筛网,本地采购能不能直接替代?
Kwame A.
认证用户 · 钻井物资采购
Three mud pumps on site change valve bodies and seats every 400 hours, and screens run about 40 pieces a week.
Looking at onshore Niger Delta blocks, local suppliers can only do seats and some screens; the material certificate lists ordinary alloy steel without a hardness curve.
Looking at onshore Niger Delta blocks, which tests should alternatives pass, and which pressure-retaining parts must stay with the original or authorised channel?
Discussion (3)
Chidi N.认证用户 · 设备工程师2026-07-17
What we see at Port Harcourt is that test hardness and dimensional tolerance on seats first, then inspect after 200 hours; do not swap the whole batch at once.
Fatou D.认证用户 · 固控服务工程师2026-07-18
What we see at Port Harcourt is that on screens, check weave and tension dimensions; correct aperture with wrong tension halves the life.
Ifeanyi O.认证用户 · 安全与合规顾问2026-07-19
In Port Harcourt, do not substitute pressure-retaining items such as safety valves and BOPs; missing certificates affect insurance and release at acceptance.