莫桑比克鲁伍马盆地气田伴生气发电,和柴油机组比该怎么算账?
Amina B.
认证用户 · 场站动力主管
The processing station runs three 500 kW diesel sets about 500 hours a month, with fuel trucked from Pemba.
Associated gas swings from about 12,000 m³ by day to 6,500 m³ at night, and a full sulphur analysis has not been done.
In Pemba, should we start with gas gensets or go straight to CCHP, given the present load profile?
Discussion (3)
Thabo M.认证用户 · 燃气机组服务工程师2026-06-16
In Pemba, do the full gas analysis first; high sulphur shortens the overhaul interval noticeably, and that cost cannot be skipped.
Yasmine K.认证用户 · 能源项目经理2026-06-17
Looking at Rovuma Basin gas fields, with an electrical load only, gas gensets are the steadier first step; CCHP should wait for a firm heat demand, otherwise the waste heat is thrown away.
Chidi N.认证用户 · 电气工程师2026-06-18
Size on the lowest stable flow, 6,500 m³, and cover peaks with diesel; do not let gas swings become shutdowns.