Energy & power circleCongo - Kinshasa2026-10-20

2 MW mine substation: how to lock transformer and genset lead times?

P

Paulo M.

Verified member · Project chief engineer

A new 2 MW plant at the mine: transformer 22 weeks, gensets 16, civils 20.

The plan is nine months to power; the schedule now runs close to ten.

How can we compress it, or supply power temporarily?

Discussion (3)

  • Ahmed Ben SalahVerified member · Service engineer2026-10-21

    The transformer is the long pole; two 1 MVA units in parallel can arrive in about 12 weeks.

  • Grace W.Verified member · Project chief engineer2026-10-22

    Renting a 1.25 MW set as a bridge is common and costs less than standing idle.

  • Kwame A.Verified member · Mine equipment manager2026-10-23

    Start civils and foundations early; waiting for equipment adds two more months.