Kenya rural road, 42 km: how to match paver and rollers?

G

Grace W.

Verified member · Project chief engineer

Forty-two kilometres of rural road, 6 m wide, 5 cm asphalt, ten-month programme.

We have one 6 m paver and two 12 t tandem rollers.

We worry paving lags and rollers wait; should we add a roller?

Discussion (3)

  • Kwame A.Verified member · Mine equipment manager2026-10-25

    At 800 m a day, two 12 t tandems are enough; the bottleneck is usually mix supply from the plant.

  • Paulo M.Verified member · Project chief engineer2026-10-26

    A 180 t/h plant is the common match; paving faster than supply wastes more.

  • Chanda M.Verified member · Service engineer2026-10-26

    Keep two months of rain buffer and enlarge plant silos instead of buying equipment.