Kenya rural road, 42 km: how to match paver and rollers?
Grace W.
Verified member · Project chief engineer
Forty-two kilometres of rural road, 6 m wide, 5 cm asphalt, ten-month programme.
We have one 6 m paver and two 12 t tandem rollers.
We worry paving lags and rollers wait; should we add a roller?
Discussion (3)
Kwame A.Verified member · Mine equipment manager2026-10-25
At 800 m a day, two 12 t tandems are enough; the bottleneck is usually mix supply from the plant.
Paulo M.Verified member · Project chief engineer2026-10-26
A 180 t/h plant is the common match; paving faster than supply wastes more.
Chanda M.Verified member · Service engineer2026-10-26
Keep two months of rain buffer and enlarge plant silos instead of buying equipment.