Kenya bridge piles: rotary or percussion drilling, which is faster?
Kwame A.
Verified member · Mine equipment manager
Twenty-four bridge piles, 1.2 m diameter, 28 m deep, clay over sandstone.
Percussion takes three days a pile and the programme will not close.
How much faster is rotary, and can it cut the sandstone?
Discussion (3)
Samuel O.Verified member · Service engineer2026-09-14
In clay, rotary drills a pile a day; sandstone depends on strength, and above 60 MPa you need a rock tool or percussion.
Grace W.Verified member · Project chief engineer2026-09-15
Rotary needs slurry and hard standing; do not overlook mobilisation. We lost a week on that.
Ade O.Verified member · Procurement lead2026-09-16
A rotary rents at USD 28,000 a month; saving a month of programme already pays for it.