肯尼亚钻机模块海运,蒙巴萨港绑扎要注意什么?
Fatou D.
认证用户 · 项目物流经理
The largest module is 13 m long, 3.2 m wide and 28 t, carried on a breakbulk vessel.
In Mombasa, the carrier wants a lashing calculation, but we only hold the maker's general arrangement drawing.
On our side in Mombasa, who normally issues the lashing plan, and what should be prepared ahead of discharge?
Discussion (3)
Kwame A.认证用户 · 大件海运操作2026-10-18
Looking at Turkana and coastal exploration blocks, the carrier or a lashing company issues it; you supply centre of gravity, lifting points and support positions.
Amina B.认证用户 · 港口协调2026-10-19
Check bridges and port roads early for over-width loads; the width limit inside Mombasa can be harder than the vessel.
João P.认证用户 · 卸船与陆运2026-10-20
What we see at Mombasa is that line up lifting gear and trailers before discharge; demurrage is billed by the day and costs far more than lashing.
Recent replies in this thread, ordered by posting time