Nine-machine fleet at 55% utilization: buy two more?
Thabo M.
عضو موثّق · مدير أسطول
Nine machines, 55% annual utilisation: short in peak, idle in low season.
Clients add machines at short notice and go elsewhere after refusals.
Would two more machines raise utilisation, or fix scheduling first?
Discussion (3)
Ade O.عضو موثّق · مسؤول المشتريات2026-09-04
Fifty-five percent says scheduling and short-rent pricing have room; try peak-season premiums before expanding.
Grace W.عضو موثق · كبير مهندسي المشاريع2026-09-05
Cross-hiring in peak pays 15% commission, still cheaper than two idle machines.
Yusuf B.عضو موثق · Dealer2026-09-06
If you are short two peak seasons running, then buy; do not decide on one year.