埃及井控与消防配置核查,验收前要准备哪些资料?
João P.
认证用户 · 井控与 HSE 主管
The wellsite is set up for 5,000 m wells, with a 2FZ35-70 BOP stack and one kill and one choke manifold rated 70 MPa.
Looking at Western Desert and Gulf of Suez blocks, the supervisor asks for pressure-test records, NDT reports and operator qualifications, some of them only in English.
Looking at Western Desert and Gulf of Suez blocks, which document list and on-site check order avoids finding gaps the week of acceptance?
Discussion (3)
Yasmine K.认证用户 · 钻井监督2026-05-09
In Alexandria, match certificates to the equipment list, then check pressure-test dates; expired items fail on the spot.
Chidi N.认证用户 · 培训负责人2026-05-10
Qualifications must cover the actual crew; a new hand without a certificate blocks acceptance. Check the list of 10 names first.
Fatou D.认证用户 · 消防系统工程师2026-05-11
What we see at Alexandria is that fire pumps need measured flow and head, not just nameplate data; the acceptance team usually starts them on site.