Today we run two crushing stages plus one ball mill at 800 t/day and want 1,200 t.
We suspect screening: the undersize runs coarse, mill feed is too big and throughput stalls.
Budget covers one stage only. If we add screening first, will the mill choke even more?
Discussion (3)
Paulo M.عضو موثق · كبير مهندسي المشاريع2026-10-22
Start with a screening efficiency test. If undersize is more than 15% coarse, screens and spray water both need work, and the fix is cheap.
Mwila K.عضو موثق · مدير معدات المناجم2026-10-23
We expanded screening first and mill throughput rose 18%, but the feed bin was too small and we had to add a conveyor later. Count both.
Chanda M.عضو موثّق · مهندس خدمات2026-10-24
Adjust mill liners and ball charge at the same time; screening alone will not lift output while the mill stays under-loaded.