Côte d'Ivoire variation: how to claim idle plant costs?

A

Ade O.

Verified member · Procurement lead

The client changed the alignment; work stopped for 18 days and nine machines stood idle.

The contract only grants a time extension, with no idle-cost clause.

What documents are needed, and on what basis is it calculated?

Discussion (3)

  • Grace W.Verified member · Project chief engineer2026-08-30

    Change order, stop notice and site records of the machines form the base; send notice early.

  • Paulo M.Verified member · Project chief engineer2026-08-31

    Claiming 60 to 70% of the shift rate is common, covering depreciation, insurance and standby crew.

  • Fatou D.Verified member · Procurement lead2026-09-01

    Photograph daily and get it signed; material assembled later is usually rejected.