Côte d'Ivoire variation: how to claim idle plant costs?
Ade O.
Verified member · Procurement lead
The client changed the alignment; work stopped for 18 days and nine machines stood idle.
The contract only grants a time extension, with no idle-cost clause.
What documents are needed, and on what basis is it calculated?
Discussion (3)
Grace W.Verified member · Project chief engineer2026-08-30
Change order, stop notice and site records of the machines form the base; send notice early.
Paulo M.Verified member · Project chief engineer2026-08-31
Claiming 60 to 70% of the shift rate is common, covering depreciation, insurance and standby crew.
Fatou D.Verified member · Procurement lead2026-09-01
Photograph daily and get it signed; material assembled later is usually rejected.