Círculo de Ingeniería MineraChile2026-10-28

Atacama mine desalination: pipeline or storage tanks first?

A

Ana C.

Miembro verificado · Ingeniero de proyectos mineros

The Atacama mine is expanding, and existing water supply is at capacity while desalination is still in front-end design.

The concentrator needs more water in Q3 next year, but the plant is at least two years away, leaving a 12-month gap.

Should we build tanks, lay the pipeline, or use temporary supply first?

Discussion (3)

  • Pedro M.Miembro verificado · Gerente de logística2026-10-29

    Quantify the production loss from the water gap. Temporary supply is expensive but reversible; an early pipeline may conflict with the final route.

  • Marek P.Miembro verificado · Jefe de obra2026-10-30

    High-altitude pipeline testing and flushing take longer; add at least two months to a lowland schedule.

  • Ahmed S.Miembro verificado · Ingeniero de aguas2026-10-31

    Tanks can come first, but lock the final water quality and flow or the connections will be rebuilt.

Respuestas recientes en este hilo, ordenadas por fecha de publicación

Unirse a la discusión

Inicia sesión para responder; el contenido aparece tras la revisión.

Iniciar sesión para responder