The Atacama mine is expanding, and existing water supply is at capacity while desalination is still in front-end design.
The concentrator needs more water in Q3 next year, but the plant is at least two years away, leaving a 12-month gap.
Should we build tanks, lay the pipeline, or use temporary supply first?
Discussion (3)
Pedro M.Verifiziertes Mitglied · Logistikleiter2026-10-29
Quantify the production loss from the water gap. Temporary supply is expensive but reversible; an early pipeline may conflict with the final route.
Marek P.Verifiziertes Mitglied · Bauleiter2026-10-30
High-altitude pipeline testing and flushing take longer; add at least two months to a lowland schedule.
Ahmed S.Verifiziertes Mitglied · Wasserbauingenieur2026-10-31
Tanks can come first, but lock the final water quality and flow or the connections will be rebuilt.