Burkina Faso shift billing: fuel by actual use or by quota?

A

Ade O.

عضو موثّق · مسؤول المشتريات

Earthworks are billed per shift; the client allows 120 L, we measure 145.

The gap is haul distance: 260 m one way against 150 m in the quota.

The contract says nothing about fuel. What is the strongest basis for a supplement?

Discussion (3)

  • Thabo M.عضو موثّق · مدير أسطول2026-10-07

    Put shift logs and fuel slips on the table and convert to actual distance and cycles; stronger than arguing over the quota.

  • Grace W.عضو موثق · كبير مهندسي المشاريع2026-10-08

    Write the measurement method into the supplement: dispenser output minus remaining fuel, signed by both sides, reconciled monthly.

  • Kwame A.عضو موثق · مدير معدات المناجم2026-10-08

    Tiered pricing by haul distance also works: a premium beyond 200 m is easier for the client to accept and cuts disputes.